USM Baseball Field Progress Report
(in reverse chronological order)

September 17, 2003 - Paving the Pathways

September 9, 2003 - Final Construction is Underway!

August 28, 2003 - Excavating for landscaping!

July 31, 2003 - Bricking is complete on pressbox and backwalls

July 17, 2003 - Pressbox structure in place; brick facings being applied

July 8, 2003: Working on the Pressbox

June 27, 2003: The seats are finished!

June 20, 2003: Seat frames being installed!

May 14, 2003: a lot of work's been done!

April 10, 2003: We're playing on it and it's looking just fine!

March 20, 2003: Spring is here; doesn't look a lot like baseball season but it's looking a lot more like a baseball stadium!

October 7, 2002: Base has been poured.

September 25, 2002: Backwalls and foundations have been poured.

August 26, 2002: Creating the superstructure - back wall and post bases.

May 7, 2002: Dugout roofs poured, forms laid for grandstrand structures.

April 24, 2002: New backstop poles; working on the brick facades.

April 18, 2002: It's starting to come together.

April 12, 2002: Equipment rooms are roofed and framed; work continues on and behind the backstop.

April 9, 2002: The season's underway and the work continues.

April 4, 2002: The home stretch!

March 29, 2002: They're working fast to get it ready!

March 24, 2002: It doesn't look a lot like baseball weather but construction continues apace.

March 20, 2002: Work on field-level structures continues.

March 11, 2002: Continuing to dig; building the 1st base dugout.

March 7, 2002: Former structures are moved or demolished; preparing and blasting.